Nordex Delta 4K Type 1 maintenance in Ukraine
The Northon team completed scheduled Type 1 maintenance on 9 Nordex Delta 4K wind turbines in Ukraine.
Scheduled maintenance on 9 wind turbines
The project ran from 24 November 2025 to 25 March 2026 on 9 Nordex Delta 4K turbines in Ukraine. Turbine work was completed on 21 March, followed by the final project close-out and reporting period.
The campaign totalled 69 turbine-days, averaging approximately 7.7 working days per turbine. The figure covers actual Type 1 maintenance days assigned to individual turbines and excludes travel, standby and office time.
Type 1 maintenance scope
The campaign combined scheduled maintenance activities with measurements, inspections and technical-condition records. Work followed project requirements and safety rules, while detailed technical procedures remain confidential.
- scheduled wind turbine maintenance
- laser shaft alignment of the drivetrain
- inspection and service of lubrication systems
- bolted connection inspection
- functional checks and completed-work documentation
Repeatable delivery and traceable reporting
A consistent work organisation method supported comparable inspections across all 9 turbines. Each stage was documented, with measurements and completed activities recorded in the project documentation.