Nordex Delta 4K Type 1 maintenance in Ukraine
We have completed a scheduled maintenance campaign on 9 Nordex Delta 4K turbines in Ukraine.
The Northon team completed Type 1 maintenance on 9 Nordex Delta 4K wind turbines in Ukraine. The project ran from 24 November 2025 to 25 March 2026 and totalled 69 turbine-days of technical work.
Scheduled maintenance and specialist measurements
The scope included scheduled wind turbine maintenance, laser shaft alignment, lubrication-system service, bolted connection inspection and completed-work documentation. Detailed procedures and the wind farm name remain confidential.
69 turbine-days across 9 turbines
The average work duration was approximately 7.7 days per turbine. The calculation includes only Type 1 maintenance days assigned to specific turbines and excludes travel, standby and office time.